Step 10 · Fill the New Water Heater

Before energizing the new water heater, it must be completely filled with water. Close the drain valve at the bottom of the tank. Open the cold water supply valve to the heater. Open the nearest hot water faucet in the house and let it run. You will hear the tank filling with water. Continue to let the water run until a steady stream of water flows from the hot water faucet, indicating that the air has been purged from the tank. Close the hot water faucet. Check all water connections for leaks.

Stesso home
SearchSearchBrowseBrowseFeedFeedMy ProjectsMy Projects
Log inLog inSign upSign up

Step 10 · Fill the New Water Heater

Before energizing the new water heater, it must be completely filled with water. Close the drain valve at the bottom of the tank. Open the cold water supply valve to the heater. Open the nearest hot water faucet in the house and let it run. You will hear the tank filling with water. Continue to let the water run until a steady stream of water flows from the hot water faucet, indicating that the air has been purged from the tank. Close the hot water faucet. Check all water connections for leaks.

Videos for this step

Fill Tank, Check for Leaks, and Power OnFill Water Heater and Bleed AirFill Tank and Test for Leaks

Tools and Materials

← Project

Water Heater Installation

Step 10 of 13·2.2 hr left

Turn Off Utilities
15 minutes2 items
Drain the Old Water Heater
60 minutes3 items
Disconnect Plumbing and Venting
30 minutes3 items
Remove Old Water Heater
20 minutes2 items
Prepare the Installation Area
30 minutes2 items
Position the New Water Heater
20 minutes2 items
Connect Water Lines
30 minutes3 items
Connect Gas Line and Venting (Gas Heaters)
45 minutes5 items
Connect Electrical Wiring (Electric Heaters)
30 minutes3 items
10
Fill the New Water Heater
20 minutes1 items
11
Restore Utilities and Test
60 minutes2 items
12
Install Temperature and Pressure Relief Valve (T&P Valve)
20 minutes3 items
13
Final Inspection and Cleanup
30 minutes1 items