The presenter highlights the critical importance of proper compaction for the backfill behind the retaining wall. Using a 250-pound plate compactor, he demonstrates compacting in very short 'lifts' (layers) of approximately 2.5 to 3 inches. He explains that compacting deeper lifts (e.g., 4 inches) only compacts the top few inches, leaving the lower portion uncompacted. This leads to future settling and potential wall failure. Achieving actual complete compaction requires these short, controlled lifts. Expert commentary emphasizes that for engineered walls, proper compaction behind the drainage zone is essential to prevent problems, regardless of engineering specifications that might suggest otherwise for 'uncontrolled fill'.

Goal: Understand and apply correct compaction techniques using a plate compactor, emphasizing short lift depths to achieve full compaction and prevent future settling.

Tools and materials

  • Plate Compactor (250 lb)
  • Drainage Aggregate (Gravel)

What they say

Hide

smaller plate packers this is a 250 pound plate packer and you'll see me and blaine doing them doing really short lifts about two and a half to three inches and that's because it'll only so say we did like a four inch lift it's not going to pack that whole four inches it'll just pack the top of it and it will reach a point where it won't pack anymore and it will be you know top couple inches that are packed and the bottom couple inches won't be packed so that's why we're doing it in shorter lifts takes a little bit longer but you're getting the actual complete compaction especially if you're using a 250 pound plate packer if you're using you know one of the big boys we could do a five six inch lifts but small packer small lips that's all you gotta remember