What happens here
To address the high groundwater and prepare for the patio, the original plan involved bringing in large, 3-6 inch rip-rap (crushed rock or aggregate) as a base. This material, similar to road base used over swamps, does not require compaction as its interlocking nature provides stability and allows water to flow through. It would be layered just above the water elevation, separated by filter fabric, and then covered with structural fill to reach the final desired height for the paver patio.
Goal: Create a stable, permeable base above the water table.
Tools and materials
- Bobcat 325 Mini Excavator Bobcat — Excavating and moving soil within the pool basin
- Bobcat S250 Skid Steer Loader Bobcat — Moving and spreading rip-rap and structural fill
- 3-6 inch Rip-Rap N/A — Creating a stable, permeable base over the high groundwater
- Filter Fabric N/A — Separating the rip-rap from the structural fill and preventing mixing
- Structural Fill N/A — Bringing the elevation up to the desired level for the patio base