Establish Grade and Measure Depth
At 0:00 in
Pavers-Mastering the basics
What happens here
The first step is to establish the desired grade and depth for the paver installation. Use a string line to mark the intended path or patio area. The string line serves as a reference for the final height of the pavers. Measure the current depth from the string line to the existing ground. The goal is to achieve an excavated depth that allows for a minimum of 6 inches of compacted base material, plus the thickness of the pavers and a thin layer of bedding sand. The video shows measuring depths of around 5 inches, indicating further excavation is needed.
Goal: Set up a string line to define the paver area and measure the current depth to determine how much more excavation is required.
Tools and materials
- Stakes or Pins
- String Line
- Tape Measure