Initial Site Preparation & Demolition Removal
At 0:00 in
Massive water problems led to one disaster after another. 4 k video pt 2 of 2
What happens here
The video begins by showing an ASV RT-75 Posi-Track skid steer removing demolition debris, specifically concrete slabs, from the site. This sets the stage for phase two of the project: restoration and the implementation of a new drainage system. The debris is loaded into a large dump truck, indicating significant amounts of material being cleared from the area adjacent to the building's foundation.
Goal: The first step involves removing existing demolition debris and preparing the site for the major regrading and drainage work. This includes clearing away any remnants from previous structures or landscaping to provide a clean slate for the new drainage system.
Tools and materials
- ASV RT-75 Posi-Track Skid Steer ASV
What they say
(339 characters)Hide
What they say