What happens here

After initial grading, the skid steer operator focuses on removing unsuitable soil and spreading top dressing over the slope to prepare it for reseeding and vegetation establishment. The machine then approaches a pile of rocks, where another crew member assists by shoveling the rocks into the skid steer's bucket, prioritizing manual removal to avoid damaging existing grass. The loaded rocks are then transported to a wooded area for disposal.

Goal: Remove unsuitable soil, spread top dressing, and clear excess rocks.

Tools and materials

  • Compact Track Loader — Moving and spreading soil, loading rocks
  • Rocks N/A — Excess material to be removed
  • Shovel — Manually loading rocks into the skid steer bucket
  • Top Dressing Soil N/A — Preparing the slope for new vegetation

What they say

Hide

continues to work outside he's gotten rid of all of the unsuitable soil and now he's just got his top dressing left to gently spread over the slope so that it can be receded and vegetation can establish there's a little extra rock left over the boys want to get that cleaned up as well they try to be careful of the grass so Alex hops to shovel as much of it into the bucket as he can get [Music] they bring it out to the woods and put it with the rest of the unsuitable soil [Music] the boys go around the site touching up their ruts and leveling out any uneven areas by hand if need be