Prepare Tanks and Connect Hoses
At 7:56 in
I wish I did this 20 years ago!
What happens here
To ensure accurate mixing and efficient transfer, the team outlines the process of marking the main brine tank to indicate specific fill levels. This is especially important for the 300-gallon capacity, allowing them to measure out the 240 gallons of brine. After marking, the main tank's valve is opened, and the large hose from the VSI system is connected to pump brine into the truck's tank. The video shows the truck pulling up to the main tank, connecting the hose, and initiating the pumping process. They also discuss how to connect smaller hoses if using the transfer pump instead of the truck's built-in pump.
Goal: Mark the bulk brine tank for precise measurement, connect the transfer hose from the truck's VSI system to the bulk tank, and prepare for pumping.
Tools and materials
- Hoses
- Valves
- Brine
What they say
(1,156 characters)Hide
What they say
(1,156 characters)Auto-generated from the video audio.