The project leader explains that raising the grade is not feasible due to the location of 'wicks' or weep holes along the foundation, which are already at the high ground table. These wicks must remain exposed for the building to 'breathe' and drain properly. The current line for regrading is already slightly too high, necessitating careful planning to contour away from this elevation, ensuring the wicks remain functional and water drains effectively.
Goal: Further inspection involves examining the foundation's 'wicks' (weep holes) to understand the building's high ground table and determine grading limitations. The current grade is already as high as possible without covering these critical drainage points.