What happens here
After pipe installation, the trenches are backfilled. Dirty rock and clean rock are used, with clean rock sandwiched in the trench. A straw blanket is laid over the newly graded area to prevent erosion and aid in revegetation. The ground is then meticulously regraded to slope away from the building, ensuring water drains efficiently toward the storm sewer connection and away from the foundation.
Goal: The trenches are carefully backfilled with a combination of clean and dirty rock, then covered with a straw blanket, and finally regraded to ensure proper water flow away from the building.
Tools and materials
- Bobcat Mini Loader
- Shovel
- Clean Rock
- Dirty Rock/Soil Mix
- Straw Blanket