What happens here
Throughout the compaction process, continually use the compact track loader to grade and shape the slope. The target slope ratio is 2.5:1 (meaning for every 2.5 units of horizontal distance, there is 1 unit of vertical drop). This specific ratio is chosen to ensure the slope is stable and can easily support vegetation, which will further prevent erosion and runoff. Precision is key, as any deviation can lead to instability or drainage problems. Measure the slope periodically with a tape measure to verify accuracy.
Goal: Continuously grade and shape the new slope with the compact track loader, ensuring it meets the specified 2.5:1 ratio for stability and to facilitate vegetation growth.