Establish Final Slope and Erosion Control

3:22
15:03
54.8K views

At 3:22 in

How we rebuild a Failed Retaining wall WITHOUT adding new retaining walls 4 k video

What happens here

Once the structural fill is compacted, the final step is to grade the slope to the specified ratio, in this case, 2.5:1, to ensure long-term stability and ease of vegetation establishment. The use of a tape measure is shown to verify the accuracy of the slope. A silt fence is maintained at the base of the slope to control erosion and sediment runoff, particularly important until vegetation can take root and stabilize the soil naturally. This comprehensive approach, approved by both the city and a civil engineer, ensures that the buried retaining wall and the new slope effectively manage water, preventing hydrostatic pressure and soil movement over time. The careful attention to grading and erosion control helps to create a robust, naturally draining outdoor structure.

Goal: Fine-tune the grade of the new slope to meet engineering specifications (2.5:1 ratio) and install erosion control measures like a silt fence to protect the area until vegetation can be established.

Tools and materials

  • ASV RT-75 Posi-Track Skid Steer
  • Shovels/Rakes
  • Tape Measure
  • Silt Fence Unspecified

What they say

Hide

a job like this is not if it will work it's how do you get there to make it work we have an existing retaining wall that's in okay shape not awesome shape but okay shape and we've got to drive over it so the first step is to build a wall over the existing retaining wall to do that we're gonna put filter fabric over this Boulder wall and then drive right over it for 90 percent of the job then when we're done we're gonna remove all of that and reexpose that upper retaining [Music]