The creator cuts and installs vertical 2x4 studs between the top and bottom plates, spacing them 16 inches on center. He uses a framing nailer to secure these studs. He also incorporates horizontal blocking (often called 'fire blocking' or 'noggins') between some of the vertical studs. This blocking adds structural integrity to the wall, preventing it from wobbling, and provides additional nailing surfaces for future drywall installation. He acknowledges that some may skip blocking but chooses to add it for extra stability and a cleaner finish.
Goal: Vertical studs are placed 16 inches on center between the top and bottom plates, and horizontal blocking is added to increase the wall's rigidity and prepare it for drywall.
Tools and materials
- 2x4 Lumber
- 3 1/2 inch Framing Nails
- Framing Nailer Hitachi
- Measuring Tape