What happens here

After the subbase is properly compacted, import the base material. The recommended material is Class 5, which consists of 3/4-inch rock mixed with fines (smaller particles). This mixture has a cohesive nature, allowing it to pack tightly and remain uniform once compacted. For a typical paver patio, aim for a 6-inch deep compacted base. If the area will be exposed to heavy traffic, such as a driveway, increase the base depth to 8 to 10 inches. For commercial applications with semi-truck traffic, a base of up to 1 foot (12 inches) might be necessary. Apply the base material in multiple layers, or 'lifts', and compact each lift thoroughly with a heavy-duty compactor to achieve optimal density and prevent settling.

Goal: Install and compact the Class 5 base material to the appropriate depth for the patio's intended use.

Tools and materials

  • Heavy-Duty Plate Compactor — Compacting the Class 5 base material
  • Shovel — Spreading base material
  • Class 5 Base Material — Creating the primary load-bearing base layer

What they say

Hide

your base in so once you have your subbase compacted the next step is to import your base material I prefer to use a class 5 a class 5 is simply nothing more than a 34in rock that has fines mixed into it that have has a cohesive nature so once you pack it it stays uniform if you're going to be installing a typical PA patio or a PA driveway the depth of your base is 6 in if you're going to be driving larger trucks or larger vehicles on this driveway then you're going to want to deepen That Base to 8 or even 10 in commercial sites when we are installing the base material for semi Lanes around the Walmarts and the hivs and the Superstores that you guys frequent we use up to a foot of Base material if you open your back door and you're experiencing Frost Heath what you're going to be doing is you're going to dig all the way down to the bottom of your footing that may be 3 or 4 ft or more and you're going to replace that with pure 3/4 Clear Rock you may hear some people say oh don't do that but let me let me fill you in on something this is how we fix commercial sites so when you're putting your base material in I use two lifts I don't need to use two lifts because I'm using a 1000lb plate compactor but I'm using two lifts because that extra level of compaction ensures that my patio is going to look the same a decade from now as it did the day I installed it now you've got your