Fill Voids and Compact Base by Hand (Small Area)

9:38
15:09
124.1K views

At 9:38 in

How NOT to build a paver patio. Why they FAIL and how to do a DIY repair on landscaping. 4 k video

What happens here

Fill the cleared voids with new Class 5 base material, then add leveling sand. Use hand compaction tools (such as a basing hammer or hand tamper) to thoroughly compact the base material. When working near retaining walls, avoid using motorized plate compactors, as their vibrations can damage the wall. For these small areas, it is sometimes acceptable to use slightly more leveling sand (up to 1.5 inches) than the standard 1 inch, to blend with existing levels, but this is an exception for very small, isolated repairs.

Goal: Create a stable and level base in small, confined areas.

Tools and materials

  • Basing Hammer or Hand Tamper
  • Small Trowel or Board
  • Class 5 Base Material
  • Paver Sand (Leveling Sand)

What they say

Hide

the bottom here in the front so if you have a patio that butts right up to a retaining wall this is very common because you're not actually supposed to compact right up behind a retaining wall you're supposed to actually leave about three feet and this becomes problematic when a paver patio which needs a hundred percent compaction putts right up to a retaining wall it's not uncommon also another thing that can create problems like this is animals they'll dig and burrow underneath the paver patio and create their own void spaces so but there is a way to fix and repair this it's not the end of the world you have to use hand compaction behind a retaining wall meaning you still have to compact behind it because if you let that go it's going to create problems down the road but one of the things that you need to look at in this area is you've seen that pipe when they installed that swimming pool that's behind the guys while they're working whoever installed that pipe didn't compact around their pipe and that created the void spacing which created the settlement issues which created the patio failure when you give a mouse a cookie and so on and so forth so we've taken the time to compact just using light hand hand compaction equipment we can use a basing hammer you can use a packing plate you don't want to use motorized compaction equipment behind your retaining wall because you can blow out that retaining wall and then not only are you repairing a patio you could also be potentially