Subsequent Courses and Backfilling
At 2:06 in
Crazy Neighbor Loses it & Calls the building Inspector 5 times!
What happens here
Subsequent courses of retaining wall blocks are stacked on top of the previous layer, interlocking with pins or lips on the blocks. Each course is leveled and aligned carefully. After every 1-2 courses (or as per design), the area behind the wall is backfilled with gravel around the perforated pipe and then with suitable soil. Compaction of the backfill is essential to prevent future settling and ensure proper drainage. Geogrid layers are incorporated at specified intervals (e.g., every 2-3 courses) to strengthen the soil mass and enhance the wall's stability.
Goal: Following the first course, additional courses of retaining wall blocks are stacked, leveled, and backfilled with gravel and soil, incorporating geogrid as specified.
Tools and materials
- Geogrid
- Gravel
- Level
- Plate Compactor
- Rakes
- Retaining Wall Blocks
- Rubber Mallet
- Shovels
- Soil
What they say
(260 characters)Hide
What they say
(260 characters)Auto-generated from the video audio.