Prepare Base for Blocks

14:02
17:48
56.1K views

At 14:02 in

Bad Start on the First Day

What happens here

After installing the French drain, spread a final layer of drainage rock (typically gravel or crushed stone) to form a level bed for the first course of blocks. Compact this layer thoroughly using a vibratory plate compactor to create a firm, stable foundation. For wet or unstable soils, incorporate a layer of geogrid into the base. Geogrid acts as a large 'snowshoe', interlocking with the aggregate to distribute weight and prevent settlement, especially critical in areas prone to a high water table or freeze-thaw cycles. Ensure the base is perfectly level, using a long level or a laser level, as this will dictate the stability and appearance of the entire wall.

Goal: Create a stable and level base for the first course of cinder blocks by compacting the drainage rock and incorporating geogrid for stability.

Tools and materials

  • Laser Level
  • Plate Compactor
  • Shovel
  • Drainage Rock (Crushed Stone)
  • Geogrid

What they say

Hide

that's because that grid acts as a big snowshoe oh decided to uh put a drain box in here now new guys recommendations i say i agree uh drain box has got to go right in here eventually and with our base being in this area and they're really kind of starting out here we're gonna have to put one in now yeah for sure we so we're in minnesota and we can't hard pipe the drain box in from the downspout we've got to leave an air void and that what that air void does it allows allows for freeze and thaw um if we hard pipe it it could back up and the whole system could freeze going all the way up the house tear the entire downspout off actually can rip the gutters and downspout right out um that base has that geogrid in it