Once the first course is complete and perfectly level, begin stacking the next courses. Typically, each new block is offset from the one below it, creating a staggered pattern (like bricks) to enhance stability and distribute pressure. Regularly check the level of each block and course, both front-to-back and side-to-side, using a level. Tap blocks into place with a rubber mallet as needed. Ensure that the backfill (drainage rock and soil) is added behind the wall as layers are built up. This provides counter-pressure and additional support to the wall. Continue this process, building the wall course by course, until the desired height for the raised bed is achieved. The video implies that multiple courses are laid to build the wall.

Goal: Stack subsequent courses of cinder blocks, offsetting joints and maintaining level and alignment for a stable, aesthetically pleasing raised bed.

Tools and materials

  • Cinder Blocks (Versa-Lok Standard)
  • Gloves
  • Level
  • Rubber Mallet
  • Shovel
  • Drainage Rock