Workers continue to dig a trench along the building foundation. They install steel edging along the edge of the newly graded area, using stakes to secure it in place. A laser level is consistently used to check the heights and ensure the steel edging maintains the desired pitch away from the building. Alex explains that the goal is to achieve an appropriate pitch that accounts for winter frost heaving, ensuring that even after heaving, the ground will still drain effectively away from the building. They also discuss getting the delayed utility locates resolved by directly contacting the area manager.
Goal: Install steel edging and ensure proper ground pitch for drainage and frost heave mitigation.
Tools and materials
- Laser Level — Checking the height and pitch of the steel edging and graded area
- Measuring Tape — Measuring distances and depths
- Shovels — Digging trenches
- Stakes — Securing the steel edging in the ground
- Steel Edging — Creating a durable edge for the graded area and containing materials