Screeding and Compacting the Base

12:41
16:32
100.6K views

At 12:41 in

What Most WONT SHOW! Building and PRICING a Paver Patio 4k

What happens here

Install screed rails (typically metal pipes or lumber) across the patio area, set to the desired final grade and slope. Use a screed board (a straight piece of lumber) to pull across the rails, leveling the crushed rock base material to a uniform depth. Once leveled, compact the base material using a plate compactor. Ensure sufficient moisture content in the base material for optimal compaction. Repeat screeding and compaction as necessary to achieve a perfectly smooth and dense base.

Goal: Precisely level and compact the crushed rock base material to achieve the correct grade and slope for the pavers.

Tools and materials

  • Plate Compactor (walk-behind)
  • Rakes
  • Screed Board
  • Screed Rails

What they say

Hide

deepen our base for the pavers and go to eight inches how do you account for that pricing because when you deepen the base you increase the amount of excavation spoils that you have to haul out and also the amount of material that you need to import to offset that excavation here's a formula that i've used in the past that seems to work and it's one dollar per inch per square foot let me explain if we're gonna deepen the base two inches that means every square foot surface area of that patio we can charge two more dollars per square foot if we're gonna deepen the base by three inches that means we can charge an additional three dollars per square foot on top of our regular price and that's a premium price because we've got to modify the base and modify our construction techniques and the important thing is we've got to account for those changes in the project because if we don't account for them now while we're working on the project at the end of the year our financial statements will account for those changes for us by subtracting away from our profits