Prior to mixing concrete, dig multiple post holes to the required depth using a post-hole digger. Ensure the holes are accurately spaced and aligned according to project specifications. Once the holes are prepared, transport the assembled Mud Mixer and the bags of concrete mix to the work area. Position the Mud Mixer on a stable, level surface, close enough to the first post hole to allow for easy dispensing of concrete. Connect the water supply hose to the mixer's inlet.

Goal: Dig the necessary post holes, transport the assembled Mud Mixer and concrete bags to the work area, and position the mixer near the first post hole.

Tools and materials

  • Measuring Tape/String
  • Post-hole Digger
  • Shovel
  • Water Supply Hose
  • Concrete Mix Bags ALL-STAR