Verify Utility Locates and Plan Excavation

2:38
12:39
49.7K views

At 2:38 in

Rebuilding a Collapsed retaining wall 4K

What happens here

The crew checks their utility locate information, which indicates that Center Point N XL (likely a gas utility) has marked lines in the area, while all other utilities (sewer, water, telephone) are clear. Due to the gas line, a section of the excavation will require careful hand-digging to avoid damaging the utility line.

Goal: Before starting any heavy excavation, the team reviews utility locates to confirm the absence of buried lines or to identify areas requiring careful hand-digging, especially around gas lines.

Tools and materials

  • Smartphone — Reviewing utility locate information

What they say

Hide

so they've had five days seven days five working days I don't even see where they are did they Mark anything else did they actually Mark anything I just put clear no conflict did they even come to the right address they marked over there yeah they marked that one I mean those could be also other things but a different email from CenturyLink and then you scroll down describe big area of your locate has been checked and it's clear okay we'll just hand dig behind right there because obviously we see the valve coming in right there or the meter so the gas line yeah yeah so we'll just hand dig a SWAT back there down to the footing and uh be done with it yep exactly [Music] so the first thing we got to do when we're prepping a retaining wall to rebuild it is to dig out the old wall but there's some do's and don'ts to that the first don't is don't over excavate don't dig too deep make sure you know exactly how deep you need to go and for a retaining wall like the one you see in the video we need six inches of Rock plus one block which is six inches buried that means we've got to go one foot below grade and we use the sidewalk as our great elevation so everywhere you