Backfill with Drainage Rock and Native Soil
11:07
12:39
49.7K views
At 11:07 in
Rebuilding a Collapsed retaining wall 4K
What happens here
After the first course of blocks is laid, 3/4 clear angular rock is poured behind the wall to provide essential drainage. This prevents water buildup which could otherwise compromise the wall's stability. The drainage rock typically extends up to about 4-6 inches below the top of the retaining wall. The remaining 4-6 inches are then filled with native soil, allowing for future planting of grass or other vegetation, seamlessly blending the wall into the landscape.
Goal: The area behind the retaining wall is backfilled with 3/4 clear rock for drainage, followed by a layer of native soil at the top for landscaping purposes.
Tools and materials
- Rakes — Spreading and leveling soil
- Shovels — Spreading and leveling rock and soil
- 3/4 Clear Angular Rock
- Native Soil
What they say