Quantify Lost Time Due to Unforeseen Events
At 2:04 in
Lost $14,500 on this Jobsite 4/4
What happens here
The project faces significant challenges, including a machine breakdown and several soil corrections. The first soil correction alone takes 2-3 days to devise and get approved, causing non-productive time. Subsequent snow and rain events further halt progress. Blaine highlights that while some unforeseen circumstances like soil corrections can be billed as change orders, delays caused by such events or equipment failures (e.g., Volvo machine breakdown, which temporarily halted work before an ASV skid steer could be brought in) result in unbillable lost time. These non-billable periods, combined with fixed daily overhead costs (estimated at $1000/day for the company covering insurance, rent, etc.), accumulate to substantial financial losses. Up to this point in the project, approximately 14.5 days of operational time are lost due to these compounding issues.
Goal: Document and quantify time lost due to unexpected issues such as equipment breakdowns, adverse weather conditions, and multiple soil corrections. Distinguish between project changes that are billable (change orders) and those that incur unrecoverable overhead costs.
Tools and materials
- ASV Skid Steer
- Caulk Gun with Adhesive
- Excavator (Daewoo)
- Power Broom / Sweeper (Wacker)
- Propane Torch
- Safety Helmet
- Spirit Level
- Work Gloves
- Strong Adhesive (VERSABOND) VERSABOND
What they say
(2,498 characters)Hide
What they say
(2,498 characters)Auto-generated from the video audio.