Excavate Trench and Separate Soil
At 6:53 in
It was a BAD TIME for this building inspector to show up.
What happens here
After demolition, excavate the trench for the new retaining wall. The trench needs to be wide enough (approximately 7 feet at the top) and dug in layers. As you excavate, carefully separate organic topsoil from the mineral soil, creating distinct piles. The organic material is unsuitable for structural backfill and should be kept separate. During this process, continuously check for existing frost footings along the house foundation to ensure they are not undermined, especially near the sun porch area. Use the excavator's grapple for efficient digging and material separation.
Goal: Dig the retaining wall trench and sort excavated materials.
Tools and materials
- Excavator with Grapple Attachment Daewoo — Digging the trench and separating soil
- Shovel — Fine-tuning excavation and detailed soil separation
- Mineral Soil — To be used for structural backfill
- Organic Topsoil N/A — To be separated and not used for backfill
What they say
(2,267 characters)Hide
What they say
(2,267 characters)Auto-generated from the video audio.