Manual Excavation and Berm Creation
0:51
15:01
24.4K views
At 0:51 in
Installing a Pond Start to Finish in 1 day
What happens here
The teams begin the excavation process, manually digging out the designated area for the pond and waterfall. Chris from Aquascape Inc. explains the '3-foot rule', emphasizing the importance of fanning out excavated dirt at least three feet horizontally from the edge of the pond liner. This technique prevents the formation of an unnatural 'volcanic' look and provides stable support for the rocks and liner. He also details why manual digging with a crew of 4-5 people is often more efficient and less damaging to the landscape than using heavy machinery for ponds of this size (e.g., 8x11 ft).
Goal: Excavate the pond area and build supporting berms
Tools and materials
- Shovels Various — Digging and shaping the pond and berms
- Wheelbarrows — Transporting excavated dirt
What they say
(2,272 characters)Hide
What they say
(2,272 characters)Auto-generated from the video audio.