What happens here

The process of backfilling the pool with soil begins. The operators emphasize using 'compression compaction' by driving heavy machinery (skid steer and mini excavator) over the freshly placed soil to compact it. This method ensures adequate density (aiming for 95% standard proctor density) without over-compacting, which would prevent grass from growing. They use the broken concrete pieces as the first layer of backfill, then cover with fill dirt.

Goal: Properly backfill the pool excavation with compacted soil to prevent settling.

Tools and materials

  • ASV RT-75 Skid Steer Loader ASV — Transporting and spreading fill soil, and performing compression compaction
  • Bobcat 325 Mini Excavator Bobcat — Assisting with spreading soil and compaction
  • Broken Concrete Pieces N/A — Used as the first layer of backfill in the deepest parts of the pool
  • Fill Dirt N/A — Filling the pool excavation

What they say

Hide

some places he can Blaine's got a lot of fishing to do at the very bottom of the swimming pool because that's where they pour the biggest chunk of concrete once he gets that out then he can start importing fill soil now we use compression compaction and you'll see that in this clip as we're starting to place soil you'll see is running over it with both the ASV and the mini excavator and a lot of guys will say well that's not doing anything good well actually it's and it's the opposite you see this is considered green space and we're aiming for about 95% standard Proctor density meaning we don't want to over compact this area because this is a mistake that we've made in the past if we over compact this area the customers never going to be able to grow grass it just gets like concrete and then they end up fighting it they may have to till it and try to loosen up that soil and air evade it but what we've learned if we use just the right amount of compression compaction we can get it so that it doesn't settle but it still allows grass to grow now the flip side of that coin is if we were going to be putting a foundation on this or if we're gonna be putting a hard structure like a patio or a gazebo where we can't have any settlement whatsoever any differential movement in that soil well then we're gonna use vibratory compaction and we're gonna do it in a completely different manner so before we even start a project we make sure that we know what the long term vision of the customer is for that space today we're building a backyard we don't want to over compact it and this is how we do it he's got the mini axe down there rocking and rolling back and forth right now he's just feeling around as well and Blaine is doing the exact same thing and you'll see us wash rinse and repeat this process over and over again [Music] now I've heard claims that some companies can do this entire process in one single day I have no clue how you can do everything that we do in a single day I don't care what kind of equipment you use and I don't care how many people you throw at it there's just so many details that need to be covered little things like trying to get all the pipe work out making sure that you get all the grades set the right way and a lot of other things that just don't feel right trying to rush it to me at least now for us we schedule three and a half days to remove a standard swimming pool under normal conditions but if something happens and it takes us for four and…