Estimate Labor Costs and Final Bid Price

7:59
12:53
252.7K views

At 7:59 in

How to Measure Estimate and Install Sod and Turf

What happens here

The final component of your bid is labor cost. First, estimate how many square yards of sod one person can install per hour (e.g., 50 square yards/hour). Divide the total square yards of the project by this installation rate to find the total labor hours needed (e.g., 177 sq yds / 50 sq yds/hr = 3.54 hours). Multiply the total labor hours by your hourly labor rate (e.g., 3.54 hours * $20/hour = $70.80). Then, divide this total labor cost by the total square yards to find the labor cost per square yard (e.g., $70.80 / 177 sq yds = $0.40 per square yard). Add this to your material and delivery cost to get the total expense per square yard (e.g., $2.62 + $0.40 = $3.02 per square yard). Remember to add a profit margin (e.g., 10%) on top of your total expense to ensure profitability.

Goal: Calculate labor cost per square yard and determine the final profitable bid price

Tools and materials

  • Calculator — Performing labor and final bid calculations
  • Whiteboard — Illustrating labor roles and calculations

What they say

Hide

177 square yards so we take 17 77 and then we divide it by 50 because that's how many square yard per hour this guy can put in that comes up to 3.54 hours so all that sod in this yard should be installed by one guy in 3.54 hours how much do you pay him an hour let's just say it's $20 an hour so we multiply 3.54 by 20 and that means it's going to cost us $70 to install that that side okay so now we have to convert that divide the 70 by 177 40 cents per square yard is what it's costing us so total total expense should be $32 that's your expense did you follow me we have the sad price here we have we CED out the transportation fee which came out to $150 a yard um and then we've also counted in all the other in line item all the other expenses to come up with the actual number that we need to know what it's costing us and now are you going to do this job at Cost you're the owner put some profit in there put 10% on top of it if you put 10% on this number you just simply add another 30 cents onto it so $332 a square yard it's going to vary don't go by these formulas try it and true use the idea of how to break it down and apply it to your area if you're in California what you're going to be doing for side jobs is not going to be the same so this is how I do my side jobs and you can just use this as an