Calculate Excavation Volume and Hauling Costs

15:10
25:10
347.8K views

At 15:10 in

How to do Retaining Wall Bids, Estimates and Proposals

What happens here

To calculate the volume of soil to be excavated from behind the garage wall, use the dimensions of the area: 22 linear feet (length of garage wall) * 5 feet high (exposed wall height) * 5 feet deep (distance from wall). This gives 550 cubic feet. Divide by 27 to convert to compacted cubic yards (20.37 c.y.). To account for soil fluffing when excavated, multiply by 1.25, resulting in 25.46 fluffy cubic yards. Finally, convert to tons by multiplying by 1.5 (as per speaker's estimate for soil type), which yields approximately 38 tons (roughly 3 loads). This detailed calculation supports the $4,000 excavation estimate, ensuring profitability and transparency.

What they say

Hide

on it so um I want you to look at remove the wall now you've seen we had a wall to remove and that was the first portion of the wall I divided the wall into two sections um from the garage to behind the garage was one section and that was Excavating but everything in front of the garage was a different section and in this proposal I've actually line item the removal of that area at $1,760 okay and then right below that I have actually line item the excavation to haul away the soil behind the the garage wall so we have to what they want us to do is they want us to pull that soil off from the garage wall because it's caving in they want us to haul that away and get rid of it and create that Gap that you we' seen we showed it according on the next door neighbor site okay and to do that portion of the work I want to be very specific how I did this now excavate and haul away soil to create a four to six foot Gap okay haul out 46 tons or three loads of soil between the building and the retaining wall now I'm not creating a 10 foot Gap and I'm not hauling out 80 tons of soil I have very clearly said I'm going to haul out 46 tons or three loads and I'm going to create a 4 to six foot Gap now how do I come up with a 4 to six foot Gap well the it's a simple math the length of that wall was about 22 uh linear feet the height of that bank is 5 foot and we're going to create a 5 foot cut between the two so it's 22 * 5 * 5 then you divide that that gives you cubic Fe feet then you divide that by 27 to convert to cubic yards okay and that's compacted cubic yards then you multiply by 1.25 to go from compacted cubic yards to expanded cubic yards because it automatically fluffs up as soon as you dig it out the dirt fluffs up and becomes bigger okay and then I don't haul in cubic yards I haul in cubic tons so then we're going to multiply by another factor of 13536 or maybe even 1.5 somewhere in that neck of the woods depends on the type of soil to go from cubic yards fluffed cubic yards to metric tons okay seems like a lot of math boom I'm going to try to put it in as I'm talking about it right over on the side of me here so that you have it you have a greater understanding the key component to that is I have clearly identified for $44,000 what work I'm going to do on this very specific line item okay I'm safe if anything goes wrong it's not on my back it's that way I'm protected and I've outlined it before we start with the customer so they have an understanding of what…

Auto-generated from the video audio.