After ground excavation, the layout for the deck begins. The existing small concrete patio is integrated into the design, and the goal is to extend the deck outwards. A tape measure is used to establish the desired distance from the house, and spray paint marks the outer perimeter. Wooden stakes are driven into the ground, and string is run between them to define the edges of the deck. A string level is attached to the string line to ensure everything is perfectly level. The squareness of the layout is confirmed by measuring diagonally from corner to corner.
Goal: The deck's perimeter and footing locations are marked using a tape measure, spray paint, stakes, and string to ensure squareness and proper alignment.