Compare Lump-Sum vs. Time & Material Profit
At 7:05 in
How to Bid Landscaping
What happens here
For the retaining wall repair project, the contractor initially estimated 7 total hours of work (6 labor hours plus 30 minutes travel each way) at a rate of $65/hour, resulting in a lump-sum quote of $455. However, the job was completed in just 1 hour of labor with minimal material cost (one $3 tube of glue). This meant the actual expense was approximately $15 (1 hour labor + materials), leading to a significant profit of $440 on the lump-sum bid. In contrast, if the project had been bid on a time and material basis, the profit would have only been about $55-70 (1 hour of labor plus markup on materials). This highlights how accurately estimating predictable jobs for a lump-sum bid can lead to much higher profits, compared to the lower but guaranteed profit of time and material.
Goal: Illustrate the profit potential of accurate lump-sum bids for predictable projects compared to time and material.
What they say
(2,499 characters)Hide
What they say
(2,499 characters)Auto-generated from the video audio.