Order Concrete Mix and Consider Admixtures
At 5:29 in
How NOT to pour a concrete slab, sidewalk or driveway. Beginner mistakes & Red flags! 4k video
What happens here
The consistency of the concrete, known as its 'slump', is critical. For sidewalks, a slump of 4-5 inches is common. For steps, a stiffer mix with a lower slump (around 3-4 inches) is preferred to prevent slumping during forming. When ordering concrete, specify the desired slump for the application. In hot weather, a chemical 'retarder' can be added to the concrete mix at the plant or on-site to extend the working time, giving the crew more flexibility before the concrete begins to set. If the concrete is too wet (high slump) for steps, it should be poured into the sidewalk sections first. If too dry (low slump) for the apron, water can be added *carefully* in small amounts, though this can affect the concrete's strength if overdone. Proper communication with the concrete supplier regarding slump and admixtures is key.
Goal: Specify the correct concrete slump for the project and consider admixtures like retarders for optimal workability.
Tools and materials
- Retarder (Admixture)
- Ready-Mix Concrete
What they say
(1,038 characters)Hide
What they say
(1,038 characters)Auto-generated from the video audio.