What happens here
The presenter, now in an office setting, explains the importance of understanding production rates when creating bids. He states that a standard pickup plow truck can clear 28,000 square feet per hour. He stresses that these rates vary based on snow depth and other factors. He encourages viewers to research industry-standard production rates for their specific equipment (e.g., skid loaders, backhoes) to make accurate bids. This method is common among large commercial contractors.