Backfilling and Rough Grading
At 9:38 in
Finish=Turning a Hill into a flat(er) backyard 4k
What happens here
With the retaining wall fully constructed, use the skid steer loader to begin backfilling the excavated area behind the wall. The soil used for backfill should be placed in layers and compacted to prevent future settling. Crucially, in a proper retaining wall drainage system, a layer of permeable material, such as gravel (acting as a French drain), would typically be laid directly behind the wall blocks, often with a perforated drainage pipe at the base, and then covered with filter fabric before adding soil. While not explicitly detailed in the video, this gravel layer allows water to filter through and drain away, preventing hydrostatic pressure from building up against the wall. The initial backfill helps to lock the wall into place and create the rough contours of the new upper level of the yard.
Goal: Backfill the area directly behind the completed retaining wall with excavated soil, ensuring proper compaction to create a solid and stable slope. This is where a gravel layer, forming a French drain, would typically be installed directly behind the wall to collect and divert water.
Tools and materials
- Plate Compactor
- Skid Steer Loader
- Excavated Soil
- Filter Fabric
- Gravel (French Drain material)
- Perforated Drainage Pipe