What happens here

The service wires are fully terminated within the meter socket and exterior disconnect. The two 'hot' wires come into the meter socket, and a neutral wire runs through the middle. These then feed down to the exterior disconnect. An SEU (Service Entrance Underground) cable runs from the exterior disconnect into the electrical panel in the basement, completing the house's main power feed. The PVC conduit leading up the wall has an expansion coupling to manage thermal changes. Finally, all covers are securely installed on the meter socket and exterior disconnect to protect the electrical components.

Goal: Complete internal wiring, secure enclosures, and prepare for utility reconnection.

Tools and materials

  • Exterior Disconnect Cover — Protecting the breaker and internal wiring of the disconnect
  • Meter Socket Covers — Protecting the meter and internal wiring
  • SEU Cable — Connecting the exterior disconnect to the interior electrical panel
  • Wrench Set — Securing covers and ensuring all connections are tight

What they say

Hide

[Music] So, we have our meter socket right here. 200 amp meter socket above our 200 amp exterior disconnect. See our two hot wires coming in and a neutral comes right in the middle down below to here. And then here is our exterior disconnect. You can see we got our SCU cable coming in going into the electrical panel in the basement. And over top here, we got our PVC with our expansion coupling due to the sun so it doesn't, you know, expand. We just got to bug up and uh we're almost finished, guys.