Screed Bedding Sand Layer
At 5:58 in
Easiest Patio Paver Walkway Install
What happens here
Position 3/4 inch PVC pipes parallel to each other on the compacted crushed stone base, spaced slightly less than the length of your screed board. These pipes act as guides to ensure a consistent sand depth. Dump piles of bedding sand between the pipes using the mini skid steer or by hand. Using a straight 2x4 (or dedicated screed board) spanning across the PVC pipes, drag it along the pipes to level and smooth the sand. The excess sand will be pushed forward, leaving a perfectly flat and uniform bedding layer for the pavers. Remove the PVC pipes and fill the voids with sand. Repeat this process for each section of the pathway.
Goal: Lay PVC pipes as guides, spread bedding sand over the compacted base, and use a straight edge to screed it to a precise, uniform level.
Tools and materials
- 2x4 Lumber
- Bedding Sand