What happens here

After preparing the base, the first course of retaining wall blocks is carefully laid. Workers ensure each block is level and 'toed in' by tapping it with a rubber mallet. A string line is used as a guide to maintain alignment. They repeatedly check the levelness of the blocks to prevent future issues.

Goal: Create a level and aligned foundation for the wall

Tools and materials

  • Retaining Wall Blocks Versa-Lok — Constructing the main structure of the wall
  • Rubber Mallet — Adjusting block placement without damaging them
  • Spirit Level — Checking the levelness of each block and course
  • String Line — Guiding the alignment of the blocks