Prepare for Waterproofing and Backfill
8:04
15:56
95.5K views
At 8:04 in
Day 2: Emergency Foundation repair
What happens here
Before backfilling, apply tar paper to the exterior of the foundation wall to provide a waterproofing layer. Simultaneously, transport 1.5-inch clear rock (aggregate) from an aggregate pit using a front-end loader and trailer to the job site. This aggregate will be used for effective drainage during backfilling.
Goal: Prepare the foundation wall for backfilling by applying tar paper for waterproofing and gathering drainage aggregate.
Tools and materials
- Front-end Loader
- Tar Paper
- Trailer
- 1.5-inch Clear Rock Aggregate
What they say
(471 characters)Hide