What happens here

After excavation, the crew installs a drainage system to prevent water accumulation. This involves placing geotextile fabric on the newly excavated soil, followed by sections of perforated drain tile. The drain tile is sloped to direct water away from the patio. Next, 3/4 clear rock (a permeable aggregate with no fine particles) is laid over the fabric and around the drain tile, creating a free-draining base. This material allows water to flow freely to the drain tile, preventing frost heave. The rock is compacted using a plate compactor to create a stable, level surface.

Goal: A geotextile fabric, perforated drain tile, and a permeable 3/4 clear rock base are installed and compacted to ensure efficient water drainage and prevent future freeze-thaw damage.

Tools and materials

  • 3/4 Clear Rock — Creating a permeable base layer for drainage and stability
  • Geotextile Fabric — Separating soil from aggregate and allowing water flow while preventing fines migration
  • Level — Ensuring proper slope and evenness of the base
  • Perforated Drain Tile — Collecting and channeling water away from the patio base
  • Plate Compactor Honda — Compacting the aggregate base to ensure stability
  • Shovels — Spreading and leveling the rock

What they say

Hide

so the company that originally built this had the right mind frame they put fabric down below all their class five so that they would contain the fines inside of their class five and not have them weep and not have settlement in the top of that patio but the reverse happened and the water would actually fill that channel up but what we want to do is we want to contain that water so we're going to put the fabric down a drain tile pipe in and then we're going to use three quarter clear and here's the beauty of that material three quarter clear has zero fives so this is a three quarter inch rock and this is a three quarter inch rock they just sit together and they allow the water to freely blow and pass right straight through so we found for base material three-quarter clear works beautifully all right okay now we got the class five in three core clear all right then we got our screen rails in to the straight level that we're supposed to be now we're gonna put this chip stuff that we've never worked with before at least me and alex haven't worked with it over the top of these screed rails we'll screed it out back down and then go from there okay so those granite chips are part of what we call a permeable system so if you've ever heard of permeable pavers what it is it's a very unique system of layering rocks that have zero fines in it so instead of using class 5 they use completely clear aggregate and that's just different gradients of clear rock and that's exactly what we're doing as well except we want to do a little extra insurance and we're going to put a gator mat down and that's also just going to help