After the pool basin is fully backfilled and compacted, the CTL is used for final grading. This involves spreading any remaining fill soil and black dirt evenly across the area, creating a smooth and level surface. The objective is to prepare the site for new landscaping, such as laying sod or planting a garden, ensuring proper drainage and a finished appearance. The removed pool materials, such as concrete, will ideally be sent off-site for recycling.
Goal: Complete the backfilling process by spreading topsoil and grading the entire area to prepare for new landscaping.