Skip to main content

Backfilling with Drainage Aggregate

0:06
0:23
5.9K views

At 0:06 in

2-tier retaining wall

What happens here

Once the first course (or subsequent courses) is laid, backfill the area immediately behind the blocks with drainage aggregate, such as ¾ inch crushed gravel. This aggregate allows water to drain freely, preventing hydrostatic pressure buildup behind the wall, which is a major cause of wall failure. Ensure the backfill is placed in layers (typically 6-12 inches) and compacted thoroughly. The video demonstrates this step, highlighting the gravel behind the wall.

Goal: Provide adequate drainage behind the retaining wall to prevent hydrostatic pressure.

Tools and materials

  • Plate Compactor — Compacting the drainage aggregate
  • Shovel — Placing the drainage aggregate
  • Crushed Gravel — Creating a well-draining backfill layer