To protect your new plumbing, place steel nail plates on the face of any stud where water or drain pipes pass through. Hammer them into place. These prevent accidental puncture from future drywall screws. Now, test the system. For the water lines, wrap the threads of two 1/2" NPT threaded caps with Teflon tape and screw them tightly onto the drop-ear elbow stub-outs using an adjustable wrench. Go to the main water shutoff and turn it on SLOWLY. Listen for running water. Return to the bathroom and meticulously inspect every new fitting and connection for any signs of dripping or moisture. Leave the system under pressure for at least 30 minutes. For the drain, you can cap the stub-out with a test plug and fill the new pipework with water from a higher cleanout (if available) to check the solvent-welded joints.
Step 5/5
Install Nail Plates and Test System2 min