Assessing Initial Damage to the Wall
0:09
16:06
27.5K views
At 0:09 in
Who's at Fault? You decide.
What happens here
A construction worker, Alex, is shown using a level to inspect the retaining wall. He points out that the wall is bowed out, indicating that it has been pushed out of alignment. He explains that they attempted to push it back into place. This establishes an initial observation of damage to the wall after the adjacent work by another contractor.
Goal: Identify and confirm the existing damage (bowing) of the retaining wall.
Tools and materials
- Level — Checking the vertical and horizontal alignment of the retaining wall
- Retaining Wall Versa-Lok — The structure being inspected
What they say
(120 characters)Hide
What they say
(120 characters)Auto-generated from the video audio.