Complete Layered Backfilling

0:24
0:47
1.2K views

At 0:24 in

wayyyy tight of a space. #excavator #engcon #retainingwall

What happens here

Continue the sequential process of scooping, transporting, precisely dropping, and thoroughly compacting layers of aggregate stone until the backfill behind the retaining wall reaches the desired height and density. This iterative approach ensures uniform compaction and structural integrity for the entire backfilled area. Periodically check the grade to confirm consistent slope and drainage as specified by project requirements for optimal performance of the retaining wall.

Goal: Fully backfill and stabilize the area behind the retaining wall.

Tools and materials

  • Aggregate Stone — Remaining backfill material, Excavator New Holland