Frame and Level Second Deck Section
At 13:20 in
The EASIEST Way To Build A Ground Level Deck - NO FOOTINGS!
What happens here
Construct the second section of the deck frame on the ground, similar to the first section. This section measures approximately 32 feet by 10 feet. Once framed, move it carefully into position adjacent to the first section. Level this section using a combination of hand-placed stone, shovels, and a sledgehammer to achieve precise height and stability. The individual joists within both framed sections must have full bearing on the 3/4-inch clean stone base to prevent future movement or settling. Once leveled, these sections will be securely connected using hurricane ties to create a single, robust structure.
Goal: Complete the main deck frame structure and ensure full bearing.
Tools and materials
- Cordless Drill DeWalt — Screwing frame components and installing hurricane ties
- Laser Level Bosch — Establishing consistent elevation across the entire deck area
- Shovels — Adjusting stone base beneath joists
- Sledgehammer Estwing — Adjusting joist heights by gently tapping
- Tape Measure — Measuring joist spacing and overall dimensions
- Wheelbarrow — Transporting stone for leveling
- 3/4-inch Clean Stone — Filling and leveling under joists for full bearing
- Hurricane Ties — Connecting the two framed sections together
- ProWood Pressure-Treated Lumber ProWood — Constructing the deck frame components
- Structural Screws — Securing all frame components