Site Excavation and Subgrade Preparation for Generator Pad

3:30
16:23
4.8K views

At 3:30 in

The Strategy that Beats Bigger Contractors

What happens here

The crew begins by preparing the site for the generator pad. This involves excavating the area to the required depth and ensuring the ground is properly leveled and compacted. The video shows workers using shovels and a compact track loader to move earth and prepare the subgrade. For generator installations, the pad must be on stable, well-drained ground, often requiring specific compaction tests and inspections to meet local building codes. Ensure adherence to setback requirements from property lines, windows, doors, and other structures as per local zoning and fire codes. Verify utility clearances (gas lines, water, sewer) as well.

Tools and materials

  • Compact Track Loader
  • Measuring Tape
  • Rakes/Leveling Tools
  • Shovels
  • Crushed Stone/Gravel

What they say

Hide

could do the sod while we get everything prepped for them. Seed can also be done if the customer's patient enough to wait for it. [music] >> Here's something else to think about. A lot of times the money that we're able to save a customer over here

Auto-generated from the video audio.