Skip to main content

Install Subsequent Stair Tiers

14:28
31:22
10.5K views

At 14:28 in

Teaching a Laborer TO THINK like a LEADER #1

What happens here

The helper continues the process of building the staircase by leveling subsequent sections with sand and carefully placing additional railroad ties. For each tier, the ground is prepared, compacted, and the ties are laid. The spirit level is continuously used to ensure that each tier maintains the correct level and a consistent forward pitch for effective water drainage, crucial for the longevity of the wooden steps.

Goal: Build additional tiers for the staircase, ensuring consistent height and level.

Tools and materials

  • Railroad Ties — Forming the stair treads
  • Spirit Level Milwaukee Redstick — Checking the levelness and pitch of the railroad ties
  • Leveling Sand — Creating a stable and pitched base for the ties

What they say

Hide

we got to get him right so in this case what's happening is Zach is doing a fine job of leveling each Timber individually but he's forgetting to level when you have multiple Timbers butting up to each other to level one Timber with the next Timber to make sure they're Level side to side and front to back we don't want toe kickers which is one step higher than another or lower than another we want to make sure that we have a nice consistent bed so when you're stepping down onto a Timber you feel safe and comfortable by having these Timbers at different levels or different angles it can make the entire staircase feel awkward so this is an important step to get right to make sure that every Timber marries up to the timber next to it and is consistent with the timber above it and the timber below it all right go for it let's see how you do all right we're gonna base this one out you're standing right in front of the camera that's all right Zach that's all right I'll get the camera over here okay so tell me what you're gonna do and I'll walk you through the process basically so far dumped in more dirt sand this little sand dirt and sand are not the same dirt typically has organic material in it so I just want to be careful of how we use our terminology on something like this yeah okay and brought that in and then uh brought it back up to the level because it wasn't where I had it it was just butted up to wherever it was let's let's see how we're doing let's let's uh so you're leveling this base out greeted across it okay to get it level okay so I should be able to set the timber right and if you based it this way have you leveled it this way as well pretty good pretty close but the closer you get the base the less work you'll do with the step okay how about how are we doing down here technically we should have a four foot level and we can get by we're really close but yeah we can fluff a little bit more of this in and that's the beauty part about sand is she just she works so well she just kind of kind of just what you need her to do that's that the Timber and the boat right here you know we got a little bit of a ridge right in the middle Dead on there we go now we're level this way and we are level this way so now we've got we'll have to do the final touch-ups with after we put the timber in place but we know we're close enough let's lay that Timber down and let's see how well she lays out and how close that base actually is so just because we got the sub base…

Auto-generated from the video audio.