The track loader operator commences the earthmoving process for the dam by collecting and pushing large piles of dirt and rocks into place. The presenter notes that prior to this, power lines had to be relocated. The planned dam is approximately 100 yards long and designed to be wide enough to accommodate vehicle traffic, such as a Gator utility vehicle. The intended water depth for the pond will range between 6.5 and 6.8 feet once completed.
Goal: Begin building the dam by moving cleared earth and rocks to form the base