The first course of the retaining wall blocks is being laid. The blocks are placed directly on a base of gravel, ensuring they are perfectly level using a small spirit level. A rubber mallet is used to gently tap the blocks into position and adjust their level as needed. The crew uses string lines to maintain a straight and consistent line for the wall. The blocks are then 'toed in' by adding native soil in front of and behind them, which is gently compacted using feet or a hand tamper.
Goal: Establish a level and stable first course for the retaining wall.
Tools and materials
- Gravel — Creating a level and stable base for the first course of blocks
- Hand Tamper — Compacting the soil around the blocks
- Retaining Wall Blocks Versa-Lok Standard — Constructing the wall itself
- Rubber Mallet — Gently tapping blocks into position
- Spirit Level — Ensuring the blocks are perfectly level
- String Line — Maintaining straightness and alignment of the wall
- Native Soil N/A — Backfilling and 'toeing in' the blocks