Skip to main content

Sectional Demolition and Rebuilding Strategy

17:01
24:50
53.5K views

At 17:01 in

Rebuilding a Collapsing Driveway and Retaining wall

What happens here

Instead of removing the entire retaining wall and adjacent driveway sections at once, the crew adopts a sectional approach. They demolish a portion of the old wall, then immediately begin rebuilding the new boulder retaining wall in that segment. This iterative process of 'remove a section, build a section' minimizes the exposure of the adjacent driveway to potential collapse, erosion, or weather damage, especially from heavy rainfall. This strategy adds complexity to the construction process, requiring constant communication and careful maneuvering of equipment, but significantly reduces risks to the property's existing infrastructure.

Goal: The demolition and rebuilding of the retaining wall are performed in alternating sections to protect the existing driveway and prevent widespread structural compromise.

Tools and materials

  • Daewoo 75V Excavator
  • Geotextile Fabric
  • Grapple Attachment
  • Large Boulders

What they say

Hide

the thumb down there or total grapple and just going by field to try to grab them without grabbing any more dirt than he has [Music] all right well let's give Tim a little bit of time to work and come back and visit this and see how these boulders go together and here she is pretty much wrapped up never crossed in the property lines and we had underground utilities and buried obstructions right down here let's go take a look at how they ended this wall right next to a mall so right there with stumps wrapped around the utility lines so we'll tell you how we did that in just a minute buried tree stumps and lines run it all through here so what do you got let's get the kind of stumps you got to do you around to loosen them up and the only problem with digging around them is we can't we don't have room because we couldn't do these so you never want to put a wall over a stump right ever because it's gonna rot mm-hmm and settle on you so in that situation we expand it with a big boulder which that's just one rock moving and shifting not a multiple stack of rock so that's something for these guys that take into consideration now you ground this stump down right okay so grinding it down is one way of doing it when you don't have the room to dig it out move it or and haul it away which we didn't have because this was littered with them now you hand dug and located every utility in this area didn't you Sam okay we had trenches we dug along where we were gonna be putting the boulders in and going to put down up to where we're gonna be putting boulders and now you've had a few changes on this job as well okay I'm so glad Sam except for that surprise fall in line that was like an inch under under the grass so you've had a few changes on this job that you've made along the way too right by adding geogrid into the driveway into the into the backfill of the and then I added some fabric on the back and we put class 5 up to the boulders okay so you added multiple layers of fabric really so so let's get this straight so guys watching this can understand what we did to ensure you know the job not only did your fabric behind the wall which is typical but then you fabric behind the driveway or the backfill zone over here and then this backfill Zone in the center you actually fortified with geogrid oh yeah how much it's gonna do but it always helps geogrid is like this magic bullet that makes a huge difference in patios retaining walls we've we've put fabric down and we put…

Auto-generated from the video audio.