Skip to main content

Reading the Grade and Setting a Footing

11:26
24:42
277.8K views

At 11:26 in

How to use a Rotary Laser (sponsored by Dewalt)

What happens here

With the rotary laser set up and leveled, use the grade rod with the receiver attached to find the desired grade. For a footing, this often means setting a benchmark (e.g., the top of a concrete block) and then measuring a specific depth below that. The presenter demonstrates finding the laser's level on the grade rod and uses this to establish the desired depth (e.g., 6 inches below the benchmark, resulting in an increased number on the rod). Remember that when digging deeper, the numbers on the grade rod will increase, and vice versa.

Goal: Accurately read the grade rod and set elevations for footings or trenches.

Tools and materials

  • Concrete Block — Serving as a stable benchmark for measurements
  • Grade Rod — Measuring depth and elevation
  • Green Goggles — Eye protection when viewing green laser beams directly
  • Receiver DeWalt — Detecting the laser beam on the grade rod
  • Rotary Laser Unit DeWalt — Providing a level laser plane

What they say

Hide

a typical construction site can go guys we're gonna use the top of the first block now in this case I'm just doing using this as a demonstration of how to read numbers but what I'm doing is I got my transit set on the top of our very first block laser we have to go over this rotary laser not laser rotary laser I'm gonna find where she beeps she's gonna be right about here and what you see me doing is looking directly do that just don't if you care about your vision let's see you got your green goggles up yes if you do that look directly under your rotary laser just use your green googles all right so we are right now at three foot five and a half on our on our stick now we want to go we want to get the bottom of our footing down 12 inches below that so the numbers will actually go up we're going lower so as you go lower the stick goes down your numbers go up so let's go over here the bottom of this block should 12 inches lower and where's that chisel four-foot I'm sorry thank you so we're right there we've got a we've got our setback down six inches here and we want to go six inches deeper so that puts us one foot below where our benchmark is on this wall we're going to be using the top of that block to set the rest of these block that way as we dig the

Auto-generated from the video audio.